भारत में पवन ऊर्जा की संभावना का परीक्षण कीजिए एवं उनके सीमित क्षेत्रीय विस्तार के कारणों को समझाइए ।

UPSC Civil Services (Main) Examination 2022, General Studies Paper I (GS 1), Question 7 — 10 marks, 150 words.

Syllabus line: Resources & industrial location — “Distribution of key natural resources across the world (including South Asia and the Indian sub-continent); factors responsible for the location of primary, secondary, and tertiary sector industries in various parts of the world (including India).”

GS Paper I 2022 · Q7

10 marks · 150 words Resources & industrial location X-Ray · Core #24

भारत में पवन ऊर्जा की संभावना का परीक्षण कीजिए एवं उनके सीमित क्षेत्रीय विस्तार के कारणों को समझाइए ।

Read this question in English

Examine the potential of wind energy in India and explain the reasons for their limited spatial spread.

Approach · directive: “examine / explain”

What it asks · Two parts: how large India's wind-power potential is, and why installations are concentrated in a few states.

It asks 2 things — answer each

  1. Examine: how large India's wind energy potential is, how far it has been tapped, and where it lies
  2. Explain: the reasons why wind installations have a limited spatial spread

Open with · India has the fourth highest installed wind capacity in the world, at 56.09 GW by March 2026, yet both resource and turbines cluster in a few windy states.

Cover

  • Potential: 695.5 GW at 120 m and 1,163.9 GW at 150 m hub height; target of 100 GW by 2030.
  • Growth: capacity rose from 21.04 GW (March 2014) to 56.09 GW (March 2026); offshore VGF for 1,000 MW off Gujarat and Tamil Nadu.
  • Resource geography: strong, steady winds only on coasts, gaps and open plateaus; eight states hold most potential, Rajasthan alone 284.2 GW.
  • Seasonality and land: output peaks in the monsoon months; turbines need open, unforested land and clearances.
  • Grid: windy sites lie far from load centres; weak evacuation lines and curtailment deter investors.
  • Policy and finance: early state incentives and cheapest-site auctions concentrated capacity; distribution companies pay late.
  • Way forward: the January 2026 Task Force on land and transmission, a wind RPO, repowering old turbines and offshore projects.

Close with · Taller turbines unlock the 150 m resource well beyond today's clusters; spreading them is central to SDG 7 (affordable and clean energy).

Add value (verified)

Question: UPSC's CS (Main) 2022, GS Paper I — paper ↗. Approach: Minimalist IAS, checked 16 Oct 2026 (how we verify) — UPSC publishes no model answers. ·

Model answer· 221words · Minimalist IAS

India has the fourth highest installed wind capacity in the world, 56.09 GW by March 2026, yet resource and turbines cluster in a few states.

Potential of wind energy in India

  • Gross resource: NIWE puts potential at 695.5 GW at 120 m and 1,163.9 GW at 150 m hub height.
  • Pace: capacity rose from 21.04 GW in March 2014 to 56.09 GW in March 2026; the target is 100 GW by 2030.
  • Offshore: viability gap funding covers 1,000 MW off the Gujarat and Tamil Nadu coasts.

✏️ Map to sketch in the exam · Wind potential at 150 m hub height

  • Shade: Rajasthan, Gujarat, Maharashtra, Karnataka, Andhra Pradesh, Tamil Nadu, Madhya Pradesh, Telangana = eight high-resource states (PIB 2026)

Draw on India's official outline (Survey of India boundary).

Reasons for limited spatial spread

  • Resource geography: strong winds blow only on coasts, mountain gaps and open plateaus; Rajasthan alone holds 284.2 GW.
  • Land: turbines need open, unforested land; fragmented holdings and clearances delay projects.
  • Grid: windy sites lie far from load centres; weak evacuation lines and curtailment deter investors.
  • Policy and finance: early state incentives, then auctions favouring the windiest sites, concentrated capacity; discoms pay late.

Way forward

  • Unblocking: a Task Force (January 2026) on land and transmission, a wind purchase obligation, and repowering of old turbines.

Taller turbines can tap the 150 m resource well beyond today's clusters, spreading SDG 7 (affordable and clean energy) across more states.

Prepared by Minimalist IAS to the answer standard of Shivam Singh (mentor, 7 years) · facts checked against official sources (how we verify) · updated 16 Oct 2026. UPSC publishes no model answers: compare your structure and coverage with this, then write your own.

Cite this question: UPSC CSE Mains GS-1 2022, Q7 — minimalistias.com/pyqs/mains/2022/gs1/q7 Discuss on WhatsApp

Write it now · 7 minutes for 150 words, by hand, as in the exam 07:00
Free · 3 answers on us Write this answer — get it evaluated free Handwrite it in 150 words, scan it into one PDF, and get a score and remarks from a mentor within 72 hours. Write it

Also asked on this syllabus line