Minimalist IAS
CSAT 2016 paper

UPSC CSE CSAT 2016 · Question 60 · Arithmetic: percentage, ratio, averages, time & work

Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then…

Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?

Answer & explanation

Answer: (c) 10 days

Together they do 60% in 4 days, i.e. 15% a day. Shyam alone does the other 40% in 8 days, i.e. 5% a day. So Ram does 10% a day and would need 10 days alone.

  1. Together: 60% in 4 days = 15% a day.
  2. Shyam alone: 40% in 8 days = 5% a day.
  3. Ram = 15% − 5% = 10% a day, so 100 ÷ 10 = 10 days.

Remember · Turn work into per-day percentages; rates simply add when people work together.

Question and answer: UPSC's official GS Paper II (2016, Series A) — paper ↗ · answer key ↗. Explanation: Minimalist IAS, checked 30 Sept 2026 (how we verify). ·